SOUTH FRASER ROAD PERIMETER PROJECT
M2K partnered with FTG Constructors to construct a wall for the the South Fraser Perimeter, valued at $3.5 million dollars. The retaining wall consisted of approximately 6,000 square meters of MSE Sierra Scape (TM), took approximately 50,000 cubic meters of road fill.
Project Challenges: The retaining wall was built above a busy and active roadway and was successfully completed incident free. All new underground pipes within the new wall had to be built in between the walls structural system.
Project Highlights: The retaining wall went on to become the longest of it’s kind in British Columbia.