JOHN KNOX HIGH SCHOOL PROJECT Project Works Project Works Mid Works Project is still in the works JOHN KNOX HIGH SCHOOL PROJECT M2K Construction is currently performing a site excavation within the community of New Westminster. The excavation will be developed as part...
WEST VANCOUVER BELLEVUE PROJECT Pre Project Works Project Works Completed Works Completed Works M2K Construction is currently performing a bulk excavation and shoring project, allowing for the development of a stunning new ocean view home situated within the West...
NEW WESTMINSTER PIER PARK PROJECT Project Works Mid Works Final Works M2K was hired by New Westminster to develop and expand the existing wharf situated over the Fraser River. The project was valued at $8 million dollars. The scope of work included demolition of...
IONA JETTY PROJECT Project Works Mid Works Final Works M2K Construction executed a slope reconstruction for the pre-existing Iona Island Jetty. The Jetty is approximately 4 km long and contains twin concrete pipes. The reconstruction required 70,000 tonnes of new rock...